Which responsibility does the Product Owner have in regards to the Product Backlog during the Sprint Review?

  1. To create new items for the backlog

  2. To highlight high-level PBIs and update the backlog

  3. To manage team dynamics

  4. To finalize the backlog for the next sprint

The correct answer is: To highlight high-level PBIs and update the backlog

The correct answer emphasizes the Product Owner's role in the Sprint Review, which is primarily focused on reviewing progress and making necessary adjustments to the Product Backlog based on feedback and learnings from the Sprint. By highlighting high-level Product Backlog Items (PBIs) during this event, the Product Owner ensures that the team and stakeholders maintain a shared understanding of the product’s direction and priorities. This process allows for collaborative discussions about the priorities of the backlog and any insights gained from the completed work. It’s crucial for facilitating transparency and engagement among all participants, ultimately guiding future development efforts. Thus, the Product Owner's responsibility to update the backlog with relevant insights from this review aligns with the aim of continuously refining and prioritizing the work for upcoming Sprints. The responsibilities of a Product Owner extend beyond just this event, but this particular focus during the Sprint Review is key to making informed decisions moving forward.