Prepare for the Certified Scrum Master Test. Use flashcards and multiple choice questions with hints and explanations. Ace your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following is NOT an element of Product Backlog Items (PBIs)?

  1. Value

  2. Estimate

  3. Complexity

  4. Order

The correct answer is: Complexity

The correct answer identifies complexity as not being an explicit element of Product Backlog Items (PBIs) in Scrum. Product Backlog Items are typically characterized by their value, estimate, and order, as these factors help the Scrum team and stakeholders understand what needs to be done, prioritize the work, and assess the scope of each item. Value is critical because it reflects the importance of the PBI in delivering customer satisfaction or business goals. Estimation allows the team to gauge the effort required to complete a PBI, which is essential for planning and sprint commitment. The order indicates the priority of items in the backlog, guiding the team on what to focus on next based on strategic objectives and stakeholder input. While complexity can be discussed in the context of a PBI, it is not officially recognized as a defined element within the Product Backlog itself. Complexity may influence the estimation process or discussions around how to approach a certain PBI, but it is not a standalone characteristic required for a PBI. Thus, complexity does not meet the criteria set for elements specifically defining PBIs.