Which is NOT a primary focus during the Sprint Review?

  1. Gathering stakeholder feedback

  2. Demo-ing product increments

  3. Updating the product backlog

  4. Planning next week's tasks

The correct answer is: Planning next week's tasks

The focus of the Sprint Review is primarily on inspecting the increment of work that has been completed during the Sprint and adapting the Product Backlog based on stakeholder feedback and the team’s performance. Gathering feedback from stakeholders is essential as it helps shape the direction of the product. Demonstrating how the product increment works showcases the team’s progress and allows for validation from those who have a stake in the project. Updating the Product Backlog is also a key activity during the Sprint Review since the insights gained from stakeholder feedback can inform necessary adjustments to the backlog items, ensuring they align with stakeholder needs and priorities. Planning next week's tasks, however, is not a primary focus during the Sprint Review. This type of detailed day-to-day planning typically takes place during the Sprint Planning meeting, which occurs before the Sprint begins. The Sprint Review is aimed at reflection and feedback rather than immediate task execution, making this the correct distinction in identifying what is not a focus during the review.