What is the ScrumMaster’s responsibility during Sprint Planning?

  1. To ensure the event occurs and maintain the timebox

  2. To document all team discussions

  3. To assign tasks to each Developer

  4. To conduct a retrospective

The correct answer is: To ensure the event occurs and maintain the timebox

During Sprint Planning, the ScrumMaster plays a critical role in facilitating the event and ensuring that it adheres to the timebox established for the meeting. This responsibility involves making certain that the planning session is focused, productive, and stays on schedule. By managing the timing, the ScrumMaster helps the team allocate sufficient time for discussing the sprint goal, identifying tasks, and estimating the work needed. In this context, it's essential for the ScrumMaster to foster an environment where the team members feel empowered to contribute to the planning process. Their role is not to dictate outcomes but to guide the team through the Scrum framework, enabling them to collaborate effectively. The other roles and responsibilities outlined in the choices do not align with the ScrumMaster's key functions during Sprint Planning. For instance, documenting discussions, assigning tasks, and conducting a retrospective are not part of the ScrumMaster's duties in this phase of the sprint cycle. Instead, these actions either fall under the responsibility of the team or occur during different events in the Scrum process.