What is the primary purpose of a Daily Scrum?

  1. To set the agenda for the week

  2. To share personal experiences among team members

  3. To synchronize activities and evaluate progress

  4. To present updates to stakeholders

The correct answer is: To synchronize activities and evaluate progress

The primary purpose of a Daily Scrum is to synchronize activities and evaluate progress. This daily meeting is a vital component of the Scrum framework, allowing the development team to come together regularly to discuss their work and progress towards the Sprint Goal. During this time, team members share what they accomplished the previous day, what they plan to work on next, and any obstacles they are facing. This synchronization helps ensure that everyone is on the same page, enabling effective collaboration and allowing the team to make adjustments to their plan as needed. While it might seem beneficial to set a broader agenda for the week or share personal experiences, the Daily Scrum is specifically focused on team tasks and progress, aiming to enhance transparency and accountability within the team. Additionally, updates to stakeholders typically occur in separate meetings or through specific communication channels, rather than during the Daily Scrum, where the focus is strictly on ongoing team activities.