What is the primary focus of a Sprint Review?

  1. Defining new project goals

  2. Demo-ing the tool and gathering feedback

  3. Planning upcoming Sprints

  4. Evaluating team performance

The correct answer is: Demo-ing the tool and gathering feedback

The primary focus of a Sprint Review is to demonstrate the work completed during the Sprint and gather feedback from stakeholders. This meeting serves as a valuable opportunity for the team to showcase the functionality of the product increment produced and engage with stakeholders, who can provide insights and suggestions for future improvements. Gathering feedback is crucial in the Agile process, as it allows the team to align their efforts with stakeholder expectations and make necessary adjustments to the product backlog. The collaborative nature of this event promotes transparency and fosters a shared understanding among all involved, which is fundamental to Scrum. While other options touch upon important aspects of project management, they do not represent the main objective of a Sprint Review. Defining new project goals, for instance, is more aligned with the planning stages rather than the review itself, and evaluating team performance, although relevant, is better suited for retrospective meetings rather than focusing on the product output presented during the Sprint Review.