What is the intent of adapting the product backlog during the Sprint Review?

  1. To finalize project delivery

  2. To ensure focus on the most important items

  3. To document team performance metrics

  4. To schedule future Sprint dates

The correct answer is: To ensure focus on the most important items

The intent of adapting the product backlog during the Sprint Review is to ensure focus on the most important items. This meeting is an opportunity for the Scrum Team and stakeholders to review the work that was done during the sprint and make decisions about the product's future direction. Given the feedback from stakeholders and the insights gained during the sprint, the team can re-prioritize items in the product backlog based on their value and relevance. This adaptation ensures that the Scrum Team is aligned with stakeholder expectations and is working on the features or enhancements that provide the greatest value to the customer or end users. It facilitates a responsive and flexible approach to development, emphasizing continuous improvement and incremental delivery of value, which are central tenets of the Scrum framework. The product backlog becomes a living document that evolves according to the changing needs of the project and the organization.