What is a primary focus of the ScrumMaster during Sprint Planning?

  1. To finalize the budget for the Sprint

  2. To ensure the team is working directly together

  3. To present the design specifications

  4. To gather feedback from stakeholders

The correct answer is: To ensure the team is working directly together

The primary focus of the ScrumMaster during Sprint Planning is to ensure that the team is working together effectively. This involves facilitating collaboration among team members to agree on the Sprint Goal and prioritize the Product Backlog items that will be selected for the upcoming Sprint. The ScrumMaster plays a crucial role in creating an environment where open communication and collaboration can thrive, allowing the team to align their efforts and collectively understand the work ahead. In this context, it's important to recognize that the ScrumMaster is not responsible for finalizing the budget, presenting design specifications, or directly gathering stakeholder feedback during Sprint Planning. These tasks either fall under the responsibilities of the Product Owner or occur in different phases of the Scrum process. The ScrumMaster's key responsibility is to enable the team to work cohesively towards a shared understanding of their goals for the Sprint.